403 US Data Centers Consumed More Energy Than 148 Countries

A Harvard University study published in “Nature Sustainability” covered the period from May 2024 to April 2025. According to the study, 403 massive data centers in the US consumed approximately 82 terawatt-hours of electricity. This represents 1.8 percent of the country’s total electricity consumption. That amount is equivalent to more than 80 percent of the 99 terawatt-hours of electricity sold in Michigan in 2024. Moreover, this consumption exceeds the annual consumption of 148 countries.
Hyperscale data centers are facilities with capacities of tens of MW that operate large cloud and content services. Although generative artificial intelligence has contributed to the rapid growth of these centers, not all the facilities in the study are used solely for artificial intelligence. The 25.7 million metric tons of CO2 emissions associated with the centers are close to Denmark’s annual carbon footprint. For 2018, this figure was estimated at 10.5 million metric tons. The current figure is 2-3 times higher than that level. Fossil fuels such as gas and coal supplied 53.9 percent of the electricity consumed. Gas accounted for 38.2 percent of total electricity consumption, while coal accounted for 15.2 percent. Renewable energy sources accounted for 25.3 percent, and nuclear energy accounted for 20.9 percent. Carbon emissions were estimated at 314 grams for each kWh of electricity. This is approximately 10 percent below the average for the US power grid.
Data centers are not distributed evenly across the country. The 142 facilities in Virginia consumed 21.4 terawatt-hours of electricity. The CO2 emissions they generated reached 7 million metric tons. Virginia, Oregon, Ohio and Iowa accounted for more than half of the total energy consumption in the study. In coal-dependent Wyoming, the same amount of energy generated approximately 7 times more emissions than in Oregon.
The researchers confirmed 403 data centers from among 675 candidate facilities using satellite imagery and building maps. The facilities had an average capacity of 39.9 MW, while the median was 36 MW. Because the centers’ actual electricity consumption was not disclosed, the calculation was based on maximum capacity, operating hours and capacity utilization. Emission figures were also estimated based on the energy sources used across 23 regional power grids. Because the period covered by the study ended in April 2025, the figures may not fully reflect the current situation. Capacities of hundreds or even thousands of MW are planned for new data center campuses. Projects totaling up to 189 GW are planned to enable these centers to generate their own energy off the power grid. If all the projects are built, emissions in the US could rise by 10 percent. The Energy Information Administration has completed pilot surveys in 10 states and is preparing a separate voluntary survey for the sector.